Density Test Report

Date :10/29/2024
Project No :2024C168
Client Company :CCG
Arrival Time :10/29/2024 8:00
Onsite Hours :06:30
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :sunny
Departure Time :10/29/2024 14:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
10/29/2024 248 20.3 101.5 26081 102.9 20.0 98.6 98 D6938 Pass
Location : Roadway between Lot #192 and Lot #164, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 249 21.7 122.8 26081 102.9 20.0 98.1 98 D6938 Pass
Location : Roadway between Lot #193 and Lot #213, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 250 20 101.1 26081 102.9 20.0 98.3 98 D6938 Pass
Location : Roadway between Lot #211 and Lot #197, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 251 20.3 101.3 26081 102.9 20.0 98.4 98 D6938 Pass
Location : Roadway between Lot #216 and Lot #209, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 252 19.8 121.1 26081 102.9 20.0 98.3 98 D6938 Pass
Location : Roadway between Lot #223 and Lot #206, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 253 20.2 101.1 26081 102.9 20.0 98.3 98 D6938 Pass
Location : Roadway in the front of Lot #226, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 254 19.5 101.2 26081 102.9 20.0 98.3 98 D6938 Pass
Location : Roadway in the front of Lot #224, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 255 21.2 100.9 26081 102.9 20.0 98.1 98 D6938 Pass
Location : Roadway between Lot #222 and Lot #155, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/29/2024 256 21.5 101.3 26081 102.9 20.0 98.4 98 D6938 Pass
Location : Roadway between Lot #217 and Lot #158, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, October 29, 2024
Reviewer Name / DateKenneth Mosman, November 05, 2024