Daily Field Report
Date :10/30/2024
Project No :2024C217
Client Company :Artisan
Arrival Time :10/30/2024 08:05
Onsite Hours :08:00
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :cloudy & rainy
Departure Time :10/30/2024 17:00
ASEC Technician Name :Vamsi Polisetty
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Nature walk: Lot #1035 & #1036
- The first lift of fill was started in Lot #1036 (backfill) using a CAT953K.
- Compaction was performed with a Hyundai HR70C. Due to the onset of a light rain, general probing and proof-rolling was used to verify stability.
Seven Hills: Amenities
- Upon arrival, the contractor was engaged in adding fill placement near the Pickle ball court parking are using a Komatsu PC 360LC and cut from the west of the job site. Fill was being transported with two tandem-axled dump trucks, while dozing was performed with a Komatsu D85EX.
- Proof-rolling of the boulder fill was utilized to verify stability in lieu of density testing using a nuclear density gauge
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.












Technician Signature / DateVamsi Polisetty, October 30, 2024
Reviewer Name / DateKenneth Mosman, January 15, 2025