Daily Field Report

Date :11/15/2024
Project No :2024C202
Client Company :CCG
Arrival Time :11/15/2024 07:15
Onsite Hours :01:30
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Clear sky and sunny
Departure Time :11/15/2024 08:45
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Upon arrival, it was discovered that the site had encountered 1.5 inches of rain overnight and the surficial soils were found to be saturated.   Fill placement was not performed today (and no compaction testing performed).  Contractor elected to terminate grading activities today until the site dries out.

Please contact us if you have any questions regarding this report or of the density test results.

 

 

 

Picture depicting muddy and wet soil

Technician Signature / DateSolomon Cherie, November 15, 2024
Reviewer Name / DateKenneth Mosman, January 09, 2025