Daily Field Report
Date :11/15/2024
Project No :2024C168
Client Company :CCG
Arrival Time :11/15/2024 9:30
Onsite Hours :02:30
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :cloudy
Departure Time :11/15/2024 12:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- The placement and compaction of backfill soils for the water line in front of Lots #235 through #238 and Lot #181 and Lot #182 was planned for this day.
- Due to the previous rain the day before, the contractor did not backfill due to wet materials.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.



Technician Signature / DateAminullah Azimi, November 15, 2024
Reviewer Name / DateKenneth Mosman, January 11, 2025