- Concrete Test Report Report ID: 74660
- Edit Download Report
Concrete Test Report
Date :12/20/2024
Project No :2024C202
Client Company :CCG
Arrival Time :12/20/2024 07:30
Onsite Hours :
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Sunny
Departure Time :12/20/2024
ASEC Technician Name :Solomon Cherie
Concrete Placement Information
Location(S):
N/A
Testing:
1 Set of concrete specimens (7 per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The specimen will remain on site for the initial 24-48 hrs curing.
Compliance:
Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)
Deviations and/or noncompliances were noted during the field placement (refer to remarks below)
Specimen
Pick Up: 1 Sets of concrete specimens/ 7 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Pick Up: 1 Sets of concrete specimens/ 7 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing:
Specimen were stored for the initial 24 hours.
Near the poured structure
In an insulated curing box
Other
Remarks:
Our ASEC representative was on site to observe the placement of concrete for the detention pond wall footing. A total of 57 cubic yards of concrete was placed and one (1) set of seven (7) cylinders were cast. There was considerable delay between concrete truck arrivals.
Technician Signature / DateSolomon Cherie, December 20, 2024
Reviewer Name / DateKenneth Mosman, January 10, 2025