Daily Field Report

Date :01/28/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/28/2025 09:00
Onsite Hours :01:30
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Partly cloudy
Departure Time :01/28/2025 10:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Upon arrival, our representative found the site surficial soils to be very high in moisture content (measured 34% and higher) from recent inclement weather.  After consultation with the contractor, it was decided that grading operations would be terminated for the day.

Please contact us if you have any questions regarding this report.

 

 

 

Picture depicting muddy and shining surface due to ice layer

Technician Signature / DateSolomon Cherie, January 28, 2025
Reviewer Name / DateKenneth Mosman, February 01, 2025