- Daily Field Report Report ID: 77157
- This project is inactive from admin. Download Report
Daily Field Report
Date :02/04/2025
Project No :2024C315
Client Company :J. Chapman Const.
Arrival Time :02/04/2025 08:30
Onsite Hours :-16:00
Name of the Project :Cottages at Villa Rica - Rock Blasting
Project Location :Villa Rica
Weather :Cloudy
Departure Time :02/03/2025 16:30
ASEC Technician Name :Micah Aycock
Observations/Finding
An AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The work was performed by Precision Blasting. Below are the key observations from the site visit:
Blasting Data
- Blasting operations continued along the sewer/storm line, extending south from Manhole A1 and east of Lot 40.
- Laterals #123 and #38 were included in this blast.
- The entire operation was executed in a single shot, proceeding smoothly without complications.
- A total trench area of 1880 square feet with a pay width of 8 feet (as provided by Precision Blasting) was blasted.
- The calculated trench rock volume removed was 580.86 cubic yards.
Drilling Data
- Drilling operations progressed west of Lot #123 using a trench pattern approach.
- Two drillers were operating simultaneously, increasing efficiency and ensuring a strong start for the next day’s drilling activities.
We appreciate the opportunity to assist with this project. Should you have any questions or require further clarification, please don’t hesitate to reach out. We would be happy to discuss this report with you.
Technician Signature / DateMicah Aycock, February 4, 2025
Reviewer Name / DateRamchandra Mogulla, February 11, 2025