- Daily Field Report Report ID: 77231
- This project is inactive from admin. Download Report
Daily Field Report
Observations/Finding
The aforementioned AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting. The following observations were made on-site:
Drilling Data:
There were no blasts today so the team continued drilling west along the same trench pattern where they left off previously. The drilling continued just north of lot #132 while one driller drilled the lateral for lot #132. The team ended the day with drilling a trench pattern southwest of lot #132 heading towards lot #191 and #192.
We appreciate the opportunity to assist you with this project. Should you have any questions regarding this report, please do not hesitate to contact us. We would be happy to discuss it with you.