Daily Field Report

Date :02/06/2025
Project No :2024C168
Client Company :Century Communities
Arrival Time :02/06/2025 8:00
Onsite Hours :08:30
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson, Jackson County, Georgia
Weather :sunny
Departure Time :02/06/2025 16:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • The placement and compaction of backfill soils for the sewer trench, between, MHSA3, MHSA4, MHSA5, MHSA6, MHSA7 continued this day.
  • At the time of arrival, our representative observed that work was in progress with1-foot lifts being placed and compacted using a 6-ton pad-foot and trench compaction equipment. Compaction testing was performed using the Standard Test Method for Density of Soil in Place by Drive-Cylinder (ASTM D 2937), along with general probing using a 3/8″ diameter probe rod.
  • Density test results indicate that most of the compacted materials met the project requirement of 95% of the maximum dry density obtained by a Standard Proctor ASTM 698.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, February 6, 2025
Reviewer Name / DateKenneth Mosman, February 19, 2025