Observations/Finding
The aforementioned AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting. The following observations were made on-site:
Drilling Data:
Because the weather cleared up today, precision blasting was able to continue drilling in preparation for the next blast. The drilling area followed the same pattern of trench in the center, with mass rock patterns on each side. The areas drilled were in-between lot #189/#188 and lot #57/#58. Good progress was made for next weeks blast, one driller was working on production drilling while the other was able to clean some previous drilling locations. Everything went according to plan and all drilling met with the production standards.
We appreciate the opportunity to assist you with this project. Should you have any questions regarding this report, please do not hesitate to contact us. We would be happy to discuss it with you.