Daily Field Report
Date :02/19/2025
Project No :2024C202
Client Company :CCG
Arrival Time :02/19/2025 09:30
Onsite Hours :01:00
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Cloudy and drizzling
Departure Time :02/19/2025 10:30
ASEC Technician Name :Solomon Cherie
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
Site is still very wet and muddy with onset of short rain making grading operations not feasible today. Contractor will spend time dewatering and demucking in hopes of starting up grading operations again tomorrow.
Please contact us if you have any questions regarding this report.

Picture showing muddy nature of the dirt

Picture depicting not possible to do backfill
Technician Signature / DateSolomon Cherie, February 19, 2025
Reviewer Name / DateKenneth Mosman, February 19, 2025