Daily Field Report

Date :02/24/2025
Project No :2022C205
Client Company :Pulte
Arrival Time :02/24/2025 12:00
Onsite Hours :02:00
Name of the Project :Enclave at Parkway Village
Project Location :Union City
Weather :sunny
Departure Time :02/24/2025 14:00
ASEC Technician Name :Vamsi Polisetty

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Footings Inspection (Lot #68)

A Dynamic Cone Penetrometer (DCP) test was performed on two sides of Lot #68, revealing the presence of small stones and rocks.

  • Dynamic Cone Penetrometer (DCP) observations were recorded up to a depth of 4 feet below the ground surface, with the following details:

Northwest Side: It can be noted that the area to the northwest of the job site corresponds to the Front of the site.

    • At 1 foot: 09 blows (Soft Brown sandy soil with small stones is Observed)
    • At 2 feet: 08 blows (Mix of Soft Brown and white sandy soil with small stones is Observed)
    • At 3 feet: 07 blows (Mix of Soft Brown and white sandy soil with small stones is Observed)
    • At 4 feet: 08 blows (Mix of Soft Brown and white sandy soil with small stones is Observed)

SouthEast Side: It can be noted that the area to the Southeast of the job site corresponds to the Back of the site.

  • At 1 foot: 06 blows (Soft Brown sandy soil with small stones is Observed)
  • At 2 feet: 08 blows (Mix of Soft Brown and white sandy soil with small stones is Observed)
  • At 3 feet: 09 blows (Mix of Soft Brown and white sandy soil with small stones is Observed)
  • At 4 feet: 07 blows (Mix of Soft Brown and white sandy soil with small stones is Observed)

General probing shows that the subgrade appears to be stable. Minor recommendations included removing loose soils from the footing. The reinforcement appears to meet job specifications for size, spacing and quantity. Rock boulders were observed in the job site.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateVamsi Polisetty, February 24, 2025
Reviewer Name / DateKenneth Mosman, April 29, 2025