Skip to content

Daily Field Report

Date :02/28/2025
Project No :2024C202
Client Company :CCG
Arrival Time :02/28/2025 07:30
Onsite Hours :08:00
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Sunny
Departure Time :02/28/2025 15:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Observed the placement of fill/grading for Lots #70and #71 (the previous temporary pond) today.  Cutting and filling continued this day. The excavating was performed by a 349E Excavator and transporting was performed by two tandem-axled 745C trucks.  Spreading was done by a 61Pxi Komatsu Bulldozer and the compaction by an 815F CAT Roller.

Storm line backfill between B1-B3 manholes compacted today whereas line B3-B5 placement is underway.

Compaction tests were performed using a nuclear density gauge. Overall, the results of density testing confirmed that fill compaction met the project and ASTM requirements. Results are attached in separate reports.

Please contact us if you have any questions regarding this report or of the density test results.

 

 

 

 

Technician Signature / DateSolomon Cherie, February 28, 2025
Reviewer Name / DateKenneth Mosman, March 09, 2025