Density Test Report

Date :02/06/2025
Project No :2024C237
Client Company :SR Homes
Arrival Time :02/06/2025 16:30
Onsite Hours :02:00
Name of the Project :Stonewood PH 4, Stone Road
Project Location :Watkinsville
Weather :sunny
Departure Time :02/06/2025 18:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/06/2025 1 24 99.2 S-02 104.0 19.1 95.4 95 D6938 Pass
Location : water line in front of Lot #79, Elv/Depth :1.5 feet below finished grade
Comment : Gauge Serial No. :85759
02/06/2025 2 24.3 97.5 S-02 104.0 19.1 93.8 95 D6938 Fail
Location : water line in front of Lot #78, Elv/Depth :1.5 feet below finished grade
Comment : In-situ moisture content much higher than optimum. Scarify, aerate and recompaction recommended. Gauge Serial No. :85759
02/06/2025 3 23.5 98.9 S-02 104.0 19.1 95.1 95 D6938 Pass
Location : water line in front of Lot #77, Elv/Depth :1.5 feet below finished grade
Comment : Gauge Serial No. :85759
02/06/2025 4 23.4 99.8 S-02 104.0 19.1 96.0 95 D6938 Pass
Location : water line in front of Lot #79, Elv/Depth :1 foot below finished grade
Comment : Gauge Serial No. :85759
02/06/2025 5 24.1 122.7 S-02 104.0 19.1 95.1 95 D6938 Pass
Location : water line in front of Lot #77, Elv/Depth :1 foot below finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, February 6, 2025
Reviewer Name / DateKenneth Mosman, April 29, 2025