Daily Field Report

Date :04/02/2025
Project No :2024C202
Client Company :CCG
Arrival Time :04/02/2025 07:30
Onsite Hours :9:15
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :
Departure Time :04/02/2025 16:45
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Observed the placement of fill/grading for Lots #48through #49today, spread by a 61Pxi Komatsu Bulldozer and compacted using a 815F CAT. Cutting continued from the adjacent roadway using a 349E CAT Excavator and hauling with two 745C dump trucks.  Compaction tests were performed using a nuclear density gauge.  General probing and proof-rolling were also performed to verify stability.

Overall, the results of density testing confirmed that fill compaction met the project and ASTM requirements. However, in-situ moisture contents are still reading higher than optimum.  Results are attached in a separate report.

Please contact us if you have any questions regarding this report or of the density test results.

 

 

 

 

Picture shows back fill area 3-5 feet to subgrade

Technician Signature / DateSolomon Cherie, April 2, 2025
Reviewer Name / DateKenneth Mosman, May 01, 2025