Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Work has continued behind Lots #224-#229. The contractor has made progress in the preparation of the retaining wall foundation.
Following inclement weather conditions on Thursday night, which left the site saturated, the contractor-initiated aeration procedures on Friday, April 10, 2025. These preparatory efforts will allow for work to resume on Monday, April 14, 2025, with a focus on backfilling and compaction operations behind the newly installed retaining wall sections along Lots #224–#229.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.