Daily Field Report

Date :04/24/2025
Project No :2024C213
Client Company :WDG
Arrival Time :04/24/2025 10:00
Onsite Hours :06:30
Name of the Project :Covington Town Center PH II
Project Location :Covington, GA
Weather :
Departure Time :04/24/2025 16:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Our ASEC representative was on site as requested and observed the grading contractor continue placing backfill for the recently excavated firewall pipeline around the perimeter of the building. The excavation was 3 feet in depth.  Compaction testing was ready for one corner of the building. Results are attached.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

 

Picture showing too wet surface for compaction.

Technician Signature / DateSolomon Cherie, April 24, 2025
Reviewer Name / DateKenneth Mosman, May 04, 2025