Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Work has continued behind Lots #224-#229. The contractor has made progress in the preparation of the retaining wall foundation and the Lots #224-#229.
Due to saturation from the previous day’s rainfall, the job site remained wet, impacting ongoing activities. Material delivery from the supplier continued throughout the day. To prepare for the next day’s production, the contractor initiated aeration of wet soils within Lots #224 to #229. Equipment utilized included a Kobelco 310LC excavator, along with Bobcat 265 and Takeuchi TL12R2 compact track loaders. By midday, the contractor focused efforts on completing the drying process.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you