Density Test Report

Date :04/22/2025
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :04/22/2025 8:30
Onsite Hours :07:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :04/22/2025 15:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/22/2025 1 25.2 94.3 2025-022 SP 103.7 16.1 90.9 90 D6938 Pass
Location : pond 1-perimeter , Elv/Depth :11.5 feet below finished grade
Comment : Gauge Serial No. :85759
04/22/2025 2 25.5 95.7 2025-023 SP 103.5 18.9 92.5 90 D6938 Pass
Location : pond -1 perimeter, Elv/Depth :11.5 feet below finished grade
Comment : Gauge Serial No. :85759
04/22/2025 3 25.3 94.4 2025-023 SP 103.5 18.9 91.2 90 D6938 Pass
Location : pond-1 perimeter , Elv/Depth :11 feet below finished grade
Comment : Gauge Serial No. :85759
04/22/2025 4 22.1 96.6 2025-023 SP 103.5 18.9 93.3 90 D6938 Pass
Location : pond-1 perimeter , Elv/Depth :11 feet below finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, April 22, 2025
Reviewer Name / DateKenneth Mosman, May 20, 2025