Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe and monitor the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site for concourse B Gate B9, grease traps this shift:
- Our ASEC representative visually inspected the installation and setup of these lanes and advised the contractor representatives of any minor corrections that were needed.
- The contractor cleaned loose rock and debris and standing water from the base.
- Baskets were found to be level, straight and secured.
- Dowel bars were found to have epoxy. Embedment length appeared to be 15 inches into concrete.
- Performed the sampling and casting of seven (7) beams.
- The pre-pour card signed by RFB rep Derick Miller, 2Mnext rep Fred, 2PK rep Luis, ATL Next rep Thierry and our representative.
Concrete Beam Sampling Data
Cast Date: May 22, 2025 Slump (inches): 2
Placement Location: Terminal B – Gate 09 Air Content: 3.0%
Modulus of Rupture: 645 psi Unit Weight: 145.8 pounds/cubic foot
Mix Number: 70JAF0534 Concrete Temperature (F): 80 degrees
Supplier: Argos Ambient Temperature (F): 63 degrees
Truck Number: 2884
Ticket Number: 32998345
Load Volume: 9 cubic yards
Batch Time: 0300 Sampled Time: 0350 Cast Time: 0355
Seven (7) concrete beam samples were cast