Density Test Report

Date :04/15/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :04/15/2025 08:30
Onsite Hours :07:30
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :04/15/2025 16:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/15/2025 1 10.4 109.4 2025-011 SP 115.0 15.5 95.1 95 D2937 Pass
Location : OCS retention pond Lot #80, Elv/Depth :2 feet below finished grade
Comment :
Technician Signature / DateSean Willett, April 15, 2025
Reviewer Name / DateKenneth Mosman, June 23, 2025