Density Test Report
Date :04/21/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :04/21/2025 08:00
Onsite Hours :05:00
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :04/21/2025 13:00
ASEC Technician Name :Sean Willett
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 04/21/2025 | 1 | 15.5 | 111.3 | 2025-011 SP | 115.0 | 15.5 | 96.8 | 95 | D2937 | Pass |
| Location : | SSMH1,0B, Elv/Depth :6 feet over pipeline | |||||||||
| Comment : | ||||||||||
| 04/21/2025 | 2 | 25.0 | 98.6 | 2025-011 SP | 115.0 | 15.5 | 85.7 | 95 | D2937 | Fail |
| Location : | SSMH1.0A, Elv/Depth :6 feet over pipeline | |||||||||
| Comment : | In-situ moisture content much higher than optimum. Recommended scarification, aeration and recompaction. | |||||||||
| 04/21/2025 | 3 | 18.3 | 100.5 | 2025-012 SP | 105.6 | 18.9 | 95.2 | 95 | D2937 | Pass |
| Location : | SSMH2.0, Elv/Depth :4 feet over pipeline | |||||||||
| Comment : | ||||||||||
Technician Signature / DateSean Willett, April 21, 2025
Reviewer Name / DateKenneth Mosman, June 23, 2025