Density Test Report

Date :06/11/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :06/11/2025 09:00
Onsite Hours :
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :06/11/2025
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
06/11/2025 9 20.5 102.0 Check
Location : Lot #1 , Elv/Depth :760
Comment : Moisture check
06/11/2025 10 17.5 98.8 2025-012 SP 105.6 18.9 93.6 95 D2937 Fail
Location : Lot #1 , Elv/Depth :760
Comment : Test results provided to contractor
Technician Signature / DateSean Willett, June 11, 2025
Reviewer Name / DateKenneth Mosman, August 05, 2025