Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Our ASEC representative was on site as requested by the contractor (Wilbanks) for the observation/testing of the placement of fill/backfill. The technician observed the contractor place 1 lift approximately 8 inches in thickness over Lots #5 through #13. The fill was placed in approx. 8-to-12-inch lifts. Only 1 lift was placed. The contractor stripped and placed topsoil on the bank in the backyards (greenspace) of these lots.
The contractor continued excavation/installation of SSMH 4.3 with a reported undercut of approximately 2 feet, bedded with No. 57 to elevation.
The contractor continued work on BE6, installed with RCP, with an invert elevation of 753.2.
The site was shut down early due to rain around lunchtime.