Density Test Report

Date :06/04/2025
Project No :2024C213
Client Company :WDG
Arrival Time :06/04/2025 08:30
Onsite Hours :02:00
Name of the Project :Covington Town Center PH II
Project Location :Covington, GA
Weather :overcast
Departure Time :06/04/2025 10:30
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
06/04/2025 1 20.2 -34.9 0 -Infinity D2937 Pass
Location : Backfill stockpile for retaining walls, Elv/Depth :Within the top 2 feet
Comment : Moisture content checks on fill for last two-foot lift (from stockpile). Well above optimum moisture content of 18.2%.
06/04/2025 2 22.4 0.0 0 NaN D2937 Pass
Location : Backfill stockpile for retaining walls, Elv/Depth :Within the top 2 feet
Comment : Moisture content checks on fill for last two-foot lift (from stockpile). Well above optimum moisture content of 18.2%.
06/04/2025 3 19.8 0.0 0 NaN D2937 Pass
Location : Backfill stockpile for retaining walls, Elv/Depth :Within the top 2 feet
Comment :
Technician Signature / DateSean Willett, June 4, 2025
Reviewer Name / DateKenneth Mosman, July 17, 2025