- Home
- Daily Field Report Report ID: 82339
- Edit Download Report
Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
1) Stripped molds from the previous day beams,
2) Observed concrete placement,
3) Measured the depth, width and length of each spall and recorded the values,
4) Observed rebar placement in each spall,
5) Cast four (4) beams,
7) Observed the 2 hour concrete beam break at 2MNEXT lab.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Spalls identified after the old material is removed

Spalls after the required rebar is put and ready for concrete pour