Density Test Report

Date :06/21/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :06/21/2025 07:30
Onsite Hours :
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :06/21/2025
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
06/21/2025 1 18.3 98.3 2025-012 SP 105.6 18.9 93.1 90 D2937 Pass
Location : Lot #168, Elv/Depth :793
Comment : Contractor continued compaction as test was performed.
06/21/2025 2 18.5 97.3 2025-012 SP 105.6 18.9 92.1 90 D2937 Pass
Location : Lot #170, Elv/Depth :793
Comment : Contractor continued compaction as test was performed. May have encountered a new fill material. Transported sample back to our lab.
Technician Signature / DateSean Willett, June 21, 2025
Reviewer Name / DateKenneth Mosman, August 06, 2025