Density Test Report

Date :07/03/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :07/03/2025 08:00
Onsite Hours :07:30
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :07/03/2025 15:30
ASEC Technician Name :Austin Coleman

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
07/03/2025 1 23.5 93.7 Field Proctor 0 Check
Location : Roadway in front of Lot #7, Elv/Depth :at finished subgrade
Comment : MDD: 97.9 and OM: 20.7
07/03/2025 2 16.5 94.4 Field Proctor 0 Check
Location : Roadway in front of Lot #16, Elv/Depth :at finished subgrade
Comment : MDD: 97.9 and OM: 20.7
Technician Signature / DateAustin Coleman, July 3, 2025
Reviewer Name / DateKenneth Mosman, August 07, 2025