Density Test Report

Date :07/15/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :07/15/2025 09:00
Onsite Hours :
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :07/15/2025
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
07/15/2025 1 21.0 94.3 2025-012 SP 105.6 18.9 89.3 95 D2937 Fail
Location : Approximately Lot #69, Elv/Depth :6 feet below finished grade
Comment : Weather affecting compaction results using cylinder ring. Will retest with a nuclear density gauge.
07/15/2025 2 19.4 93.7 2025-012 SP 105.6 18.9 88.7 95 D2937 Fail
Location : Approximately Lot #70-71, Elv/Depth :7 feet below finished grade
Comment : Weather affecting compaction results using cylinder ring. Will retest with a nuclear density gauge.
07/15/2025 3 19.4 95.0 2025-012 SP 105.6 18.9 90.0 95 D2937 Fail
Location : Approximately Lot #154, Elv/Depth :6 feet below finished grade
Comment : Weather affecting compaction results using cylinder ring. Will retest with a nuclear density gauge.
07/15/2025 4 19.3 100.8 Check
Location : Lot #156 and approximate area of Lot #70 area , Elv/Depth :6 feet below finished grade
Comment : Weather affecting compaction results using cylinder ring. Will retest with a nuclear density gauge.
07/15/2025 5 22.7 101.5 Check
Location : Lot #156 and Lot #70 area , Elv/Depth :6 feet below finished grade
Comment : Weather affecting compaction results using cylinder ring. Will retest with a nuclear density gauge.
07/15/2025 6 21.0 103.2 Check
Location : Lots #156 and #70, Elv/Depth :6 feet below finished grade
Comment : Weather affecting compaction results using cylinder ring. Will retest with a nuclear density gauge.
Technician Signature / DateSean Willett, July 15, 2025
Reviewer Name / DateKenneth Mosman, August 08, 2025