- Daily Field Report Report ID: 83315
- This project is inactive from admin. Download Report
Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Our ASEC representative was on site as requested by the contractor (Wilbanks) for the observation/testing of the placement of fill/backfill. The technician and contractor conducted a proof roll of Lots #53 through #60. Lots #50 through #52 contain a temporary retention pond that appeared to be wet from the previous night’s rain. The technician and contractor agreed to let this area aerate over the weekend before attempting a proof-roll. All low compaction areas were cut until well compacted ground was present.
The contractor then began placing fill across these lots in approximate 8 to 12 inches of thickness and compacting via sheep-foot roller.
The contractor started cutting out roadways between Lots #208 and #224 areas.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.


proof roll