As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
On the above date, the technician was on site as requested by the contractor for observation/testing of soil.
The contractor requested compaction testing of the final grade on Lots #48 through #52. Test results showed approximately 95%-97% compaction in this general area. The technician recommended to compact this area one additional time with a vibrating sheep-foot roller The contractor agreed.
The contractor continued placing topsoil along the greenspace located on these lots. Topsoil was placed in approximately 12in lifts and was compacted with a vibrating sheep’s foot roller.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.