Daily Field Report

Date :07/09/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :07/09/2025 8:30
Onsite Hours :08:00
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :sunny
Departure Time :07/09/2025 16:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, a representative from AS Engineering and Consulting (ASEC) visited the site to perform quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and approved material submittals. The following observations were made during the site visit:

The contractor prepared the slope area located to the east of Lot #92 by removing all grass, organic material, and roots to prepare a stable surface for fill placement. Following this, soils imported from an external source was delivered to the site and spread evenly across the prepared area using a dozer. In addition to the earthwork, the contractor cleaned the space between the water storage manholes using a hose to remove any accumulated debris. As part of the ongoing drainage works, the contractor also brought 8-inch corrugated HDPE “E” pipe to the site, which are intended to be used for tying in with the in the gutter downspouts to the drainage system.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, July 9, 2025
Reviewer Name / DateKenneth Mosman, August 07, 2025