Density Test Report

Date :07/29/2025
Project No :2025C215
Client Company :Artisan
Arrival Time :07/29/2025 09:30
Onsite Hours :08:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :07/29/2025 17:30
ASEC Technician Name :Safiullah Momand

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
07/29/2025 16 12.4 98.1 2025-033 SP 104.0 16.2 94.3 95 D2937 Fail
Location : 2200 Road A, Elv/Depth :3 feet to Subgrade
Comment :
07/29/2025 17 14.9 93.7 2025-033 SP 104.0 16.2 90.1 95 D2937 Fail
Location : 2000 Road A, Elv/Depth :7.5 feet from Sub grade
Comment :
07/29/2025 18 13.6 94.8 2025-033 SP 104.0 16.2 91.2 95 D2937 Fail
Location : 1900 Road A, Elv/Depth :5 feet down subgrade
Comment :
07/29/2025 19 14.0 93.9 2025-033 SP 104.0 16.2 90.3 95 D2937 Fail
Location : 1800 Road A, Elv/Depth :6 feet to Sub grade
Comment :
Technician Signature / DateSafiullah Momand, July 29, 2025
Reviewer Name / DateAdmin user, August 03, 2025