Date :08/07/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :08/07/2025 08:00
Onsite Hours :06:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :Cloudy
Departure Time :08/07/2025 14:30
ASEC Technician Name :Austin Coleman

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Our ASEC representative along with Clyde Smith of ASEC made recommendations for the amount of cut to be taken out of the curbline and backfill with GAB. For the section between Azalea Crossing  Lot #317 and #331 as well as the next closest lot going down in address on the same side of the road.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAustin Coleman, August 7, 2025
Reviewer Name / DateKenneth Mosman, August 11, 2025