- Density Test Report Report ID: 85455
- Edit Download Report
Density Test Report
Date :09/02/2025
Project No :2025C215
Client Company :Artisan
Arrival Time :09/02/2025 09:30
Onsite Hours :9:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :09/02/2025 18:30
ASEC Technician Name :Safiullah Momand
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 09/02/2025 | 1 | 16.1 | 96.3 | 2025-031 SP | 101.0 | 20.7 | 95.3 | 95 | D2937 | Pass |
| Location : | 45 ft north side of 5A manhole, Elv/Depth :4 feet below finished grade | |||||||||
| Comment : | ||||||||||
| 09/02/2025 | 2 | 17.6 | 102.0 | 2025-031 SP | 101.0 | 20.7 | 101.0 | 95 | D2937 | Pass |
| Location : | 22 ft south from 5A, Elv/Depth :8 feet below finished grade | |||||||||
| Comment : | ||||||||||
| 09/02/2025 | 3 | 13.2 | 90.8 | 2025-032 SP | 94.9 | 25.0 | 95.7 | 95 | D6938 | Pass |
| Location : | Lot #10, Elv/Depth :6 feet from finished grade | |||||||||
| Comment : | Gauge Serial No. :3430 | |||||||||
| 09/02/2025 | 4 | 12.3 | 93.4 | 2025-031 SP | 101.0 | 20.7 | 92.5 | 95 | D6938 | Fail |
| Location : | Lot #12, Elv/Depth :2 feet from finished grade | |||||||||
| Comment : | Recompation required. | Gauge Serial No. :3430 | ||||||||
| 09/02/2025 | 5 | 7.4 | 110.1 | 2025-033 SP | 104.0 | 16.2 | 105.9 | 95 | D6938 | Pass |
| Location : | Lot #11, Elv/Depth :5 feet from finished grade | |||||||||
| Comment : | Gauge Serial No. :3430 | |||||||||
Technician Signature / DateSafiullah Momand, September 2, 2025
Reviewer Name / DateKenneth Mosman, September 17, 2025