Skip to content

Daily Field Report

Date :09/08/2025
Project No :2025C224
Client Company :C. W. MATTHEWS CONTRACTING CO., INC.
Arrival Time :09/08/2025 6:30
Onsite Hours :9:00
Name of the Project :PDK Airport - RUNWAY 3R-21L KEEL REPLACEMENT
Project Location :PDK AIRPORT, DEKALB County, GA
Weather :sunny
Departure Time :09/08/2025 15:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi, visited the job site to observe the contractor’s work activities from a quality assurance standpoint. The purpose of the visit was to verify compliance with project drawings, specifications, applicable codes, approved material submittals, and to conduct QC testing in accordance with project requirements.

Observations for This Shift:

  • Compaction Testing:
    Compaction testing was performed on Section 1A between STA 1020+00 to 1028+00 on Runway 3R-21L and Section 1B between STA 1048+50 and 2180+00 using a Troxler nuclear density gauge, supplemented by general probing with a 3/8″ diameter probe rod. The density test results indicated that most of the compacted materials did not meet the project requirement of achieving a minimum of 100% of the maximum dry density, in accordance with ASTM D1557 (Modified Proctor).

  • Performed demolition for section 1B on this day.
  • Proof Rolling Observation and Performance:
    A proof roll was conducted on Section 1A between STA 1020+00 to 1028+00 on Runway 3R-21L using a fully loaded tandem axle truck. Multiple passes were made across the subgrade. During the proof roll, some significant yielding and deflection were observed throughout the tested areas, indicating insufficient subgrade stability.

  • Recommended Corrective Action:
    Due to high moisture contents resulting in insufficient compaction, it was recommended that the soil be treated with lime and recompacted to improve stability and meet project requirements.

  • Additional Personnel Present:
    The proof roll was jointly performed and observed by the undersigned (Amin Azimi), Andres Nova (QA Representative), and Tony (CWM Representative).

We appreciate the opportunity to be of service on this project. Should you have any questions regarding this report, please do not hesitate to contact us. We would be pleased to discuss our findings further.

Technician Signature / DateAminullah Azimi, September 8, 2025
Reviewer Name / DateKenneth Mosman, October 10, 2025