Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the
purpose of providing quality control inspection and testing services. Visual observation techniques were
employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.
Our ASEC representative was on site as requested by the contractor for a footing inspection/testing. Our ASEC representative conducted DCP testing and site inspection of lot 85 pod 21. There was a section of approx. 4ft long that showed low compaction via probe rod testing. It was recommended to excavate approx. 1.5ft down and fill with concrete. Besides this low compaction area, the rest of the site appears to be ready for concrete pour. All testing information was provided to the contractor.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding
this report, please feel free to contact us. We will be more than happy to discuss it with you.