Density Test Report

Date :09/29/2025
Project No :2025C216
Client Company :Artisan
Arrival Time :09/29/2025 08:00
Onsite Hours :07:00
Name of the Project :NW (Lots) Unit 4 PH 1A & 1B
Project Location :Dallas
Weather :Sunny
Departure Time :09/29/2025 15:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/29/2025 1 26.1 88.0 2025-032 SP 94.9 25.0 92.7 98 D6938 Fail
Location : Lot #7, Elv/Depth :at finished grade
Comment : Recompaction required. Gauge Serial No. :77-19952
09/29/2025 2 17.2 95.3 2025-032 SP 94.9 25.0 100.4 98 D6938 Pass
Location : Lot #9, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
09/29/2025 3 17.3 95.7 2025-032 SP 94.9 25.0 100.8 98 D6938 Pass
Location : Lot #10, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
09/29/2025 4 18.5 95.6 2025-032 SP 94.9 25.0 100.7 98 D6938 Pass
Location : Lot #11, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
09/29/2025 5 15.9 104.0 2025-036 SP 107.0 18.5 97.2 98 D6938 Fail
Location : SSMH 9A, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
09/29/2025 6 13.2 107.2 2025-035 SP 107.8 13.0 99.4 98 D6938 Pass
Location : SSMH 9A, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, September 29, 2025
Reviewer Name / DateKenneth Mosman, October 17, 2025