Density Test Report

Date :09/15/2025
Project No :2025C215
Client Company :Artisan
Arrival Time :09/15/2025 08:00
Onsite Hours :07:30
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :09/15/2025 15:30
ASEC Technician Name :Austin Coleman

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/15/2025 1 14.4 104.0 2025-033 SP 104.0 16.2 Check
Location : Roadway near Manhole A5, Elv/Depth :6 feet below finished grade
Comment :
09/15/2025 6 13.5 104.2 2025-033 SP 104.0 16.2 100.2 95 D6938 Pass
Location : Roadway near Manhole A5, Elv/Depth :6 feet below finished grade
Comment : Gauge Serial No. :29588
Technician Signature / DateAustin Coleman, September 15, 2025
Reviewer Name / DateKenneth Mosman, October 16, 2025