Date :10/17/2025
Project No :2025C211
Client Company :Pulte
Arrival Time :10/17/2025 07:30
Onsite Hours :06:30
Name of the Project :Haley's Bluff - Philadelphia Rd.
Project Location :Jasper
Weather :Sunny
Departure Time :10/17/2025 14:00
ASEC Technician Name :Sean Willett

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.

Our ASEC representative was on site by (NG Grading) for the observation/testing of the placement of fill/backfill.

The contractor continued placing approximately 6-inch lifts in the deceleration lane located by the main entrance. The soil lifts were spread using GPS on a dozer and rolled with a sheep-foot roller. Density testing was performed, and all test results were provided to the contractor. Any failed testing areas were retested after the contractor rerolled the section again.

A controlled blast was conducted in the Northwest retention pond. The blast was for the holes drilled on the previous workday. No incidents occurred.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

deceleration lane

blasted area

blasted pond North West

retention pond by deceleration lane South East

retention pond by deceleration lane South East

Technician Signature / DateSean Willett, October 17, 2025
Reviewer Name / DateKenneth Mosman, October 20, 2025