Skip to content

Daily Field Report

Date :11/21/2025
Project No :2025C244
Client Company :McCallan Group
Arrival Time :11/21/2025 07:30
Onsite Hours :10:45
Name of the Project :Cassville Rd tract, proposed Burrito Wrap
Project Location :Cartersville
Weather :sunny
Departure Time :11/21/2025 18:15
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

A silt-fence barrier was installed around the concrete storm drain structure at SD3-B, and riprap was placed around the barrier for protection. Additional riprap was also placed around the concrete headwall. The pond slope was graded and leveled, and the stockpiled soil was moved to one side.

Meanwhile, the erosion-control crew continued installing straw erosion control blankets along the SD3-A pond slopes.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateSamara Simha Reddy Kandi, November 21, 2025
Reviewer Name / DateKenneth Mosman, November 25, 2025