Daily Field Report

Date :12/10/2025
Project No :2025C211
Client Company :Pulte
Arrival Time :12/10/2025 07:30
Onsite Hours :07:30
Name of the Project :Haley's Bluff - Philadelphia Rd.
Project Location :Jasper
Weather :Sunny
Departure Time :12/10/2025 15:00
ASEC Technician Name :Sean Willett

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the
purpose of providing quality control inspection and testing services. Visual observation techniques were
employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.

Our ASEC representative was on site as requested by the contractor (NG Grading) for the
observation/testing of the placement of fill/backfill. Upon arrival to the site, the contractor started removing any frost from the previous night. Then the contractor started spreading one lift of approx. 6in to 8in in size across the commercial lot area and lots #52 – #60 and #8 – #13. ASEC watched loaded trucks roll across the lift to check for stability. There was no pumping or cracking present in this area, and the lift appears to be stable. Density testing will be conducted when the contractor places another lift to 2 lifts.

The contractor started moving topsoil for most of the day. Topsoil was taken from cut areas in the commercial lot area above the connex at the entrance and from lots #52 – #60. Topsoil was stockpiled by lots #1 – #5 to be spread on the slope of the front detention pond once it has been built up.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding
this report, please feel free to contact us. We will be more than happy to discuss it with you.

8-13 and 52-60 area

commercial lot area

commercial lot area

8-13 and 52-60 area

8- 13 and 52 - 60

Technician Signature / DateSean Willett, December 10, 2025