- Density Test Report Report ID: 88740
- Edit Download Report
Density Test Report
Date :12/17/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/17/2025 08:00
Onsite Hours :9:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :cloudy
Departure Time :12/17/2025 17:00
ASEC Technician Name :Samara Simha Reddy Kandi
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 12/17/2025 | 1 | 22.8 | 86.2 | 2025-058 | 95.2 | 18.6 | 90.5 | 95 | D2937 | Fail |
| Location : | Pond 1, Elv/Depth :4 feet below finished grade | |||||||||
| Comment : | excessive mositure content and thick lift placement(Recommend: Thin lifts, more compaction) | |||||||||
| 12/17/2025 | 2 | 18.3 | 91.5 | 2025-058 | 95.2 | 18.6 | 96.1 | 95 | D2937 | Pass |
| Location : | Pond 1, Elv/Depth :3 feet below finished grade | |||||||||
| Comment : | Recompacted and retested. | |||||||||
Technician Signature / DateSamara Simha Reddy Kandi, December 17, 2025
Reviewer Name / DateKenneth Mosman, January 30, 2026