Density Test Report

Date :12/17/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/17/2025 08:00
Onsite Hours :9:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :cloudy
Departure Time :12/17/2025 17:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
12/17/2025 1 22.8 86.2 2025-058 95.2 18.6 90.5 95 D2937 Fail
Location : Pond 1, Elv/Depth :4 feet below finished grade
Comment : excessive mositure content and thick lift placement(Recommend: Thin lifts, more compaction)
12/17/2025 2 18.3 91.5 2025-058 95.2 18.6 96.1 95 D2937 Pass
Location : Pond 1, Elv/Depth :3 feet below finished grade
Comment : Recompacted and retested.
Technician Signature / DateSamara Simha Reddy Kandi, December 17, 2025
Reviewer Name / DateKenneth Mosman, January 30, 2026