- Home
- Daily Field Report Report ID: 88757
- Edit Download Report
Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
On the above date our representative was on site to observe the pipe contractor continue installing 8″ PVC sanitary sewer pipe between manholes #10 and 11, bedding the pipe on No. #57 stone. The writer left the site early before the additional compacting equipment was delivered to site.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

8" pvc sanitary sewer pipe installation