Density Test Report
Date :12/23/2025
Project No :2025C260
Client Company :Artisan
Arrival Time :12/23/2025 11:00
Onsite Hours :04:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :Sunny
Departure Time :12/23/2025 15:00
ASEC Technician Name :Sean Willett
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 12/23/2025 | 1 | 11.3 | 90.4 | 2025-032 SP | 94.9 | 25.0 | 95.3 | 95 | D6938 | Pass |
| Location : | Cul-de-sac, Elv/Depth :869 | |||||||||
| Comment : | Gauge Serial No. :77-19952 | |||||||||
| 12/23/2025 | 2 | 10.5 | 91.7 | 2025-032 SP | 94.9 | 25.0 | 96.6 | 95 | D6938 | Pass |
| Location : | Cul-de-sac, Elv/Depth :869 | |||||||||
| Comment : | Gauge Serial No. :77-19952 | |||||||||
Technician Signature / DateSean Willett, December 23, 2025
Reviewer Name / DateKenneth Mosman, February 02, 2026