Density Test Report

Date :01/13/2026
Project No :2025C260
Client Company :Artisan
Arrival Time :01/13/2026 09:00
Onsite Hours :07:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :Sunny
Departure Time :01/13/2026 16:00
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
01/13/2026 1 14.2 102.5 2025-033 SP 104.0 16.2 98.6 95 D6938 Pass
Location : Building Lot #39, Elv/Depth :13 feet below finished grade
Comment : Gauge Serial No. :91643
01/13/2026 2 13.8 102.4 2025-033 SP 104.0 16.2 98.5 95 D6938 Pass
Location : Building Lot #38, Elv/Depth :14 feet below finished grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, January 13, 2026
Reviewer Name / DateKenneth Mosman, February 02, 2026