Density Test Report

Date :01/30/2026
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :01/30/2026 08:30
Onsite Hours :07:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :sunny
Departure Time :01/30/2026 15:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
01/30/2026 1 21.9 88.8 2025-057 92.1 25.7 96.4 95 D2937 Pass
Location : Between Point B9-B10, Elv/Depth :3 feet below finished grade
Comment :
01/30/2026 2 22.9 87.7 2025-057 92.1 25.7 95.2 95 D2937 Pass
Location : Between Points B10-B11, Elv/Depth :2 feet below finished grade
Comment :
Technician Signature / DateSamara Simha Reddy Kandi, January 30, 2026
Reviewer Name / DateKenneth Mosman, February 18, 2026