Daily Field Report

Date :02/02/2026
Project No :2025C260
Client Company :Artisan
Arrival Time :02/02/2026 11:00
Onsite Hours :05:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :sunny
Departure Time :02/02/2026 16:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

The contractor continued sanitary sewer installation between manholes #13 and #14 with excavation being performed using a Komatsu 490 excavator. Hard and fractured stone was encountered throughout the full depth of the trench. Our representative observed hammering of this sanitary sewer line trench between manholes #13 and#14. A total of 4 hours of hammering was required. Due to the depth of the excavation a steel trench box system was installed then the trench bottom was cleaned and leveled. The subgrade was prepared using GAB bedding that was placed and then an 8-inch ductile iron pipe (DIP) was installed in 20-foot lineal sections extending approximately 80 feet in the west and then backfilled and compacted using a sheep-foot vibrator.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Excavator digging hard rock from the trench

Trench box installed to protect workers

Compacting using sheep foot roller

Technician Signature / DateSamara Simha Reddy Kandi, February 2, 2026
Reviewer Name / DateKenneth Mosman, February 04, 2026