Density Test Report

Date :02/05/2026
Project No :2025C215
Client Company :Artisan
Arrival Time :02/05/2026 08:30
Onsite Hours :9:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :02/05/2026 17:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/05/2026 1 19.8 92.6 2025-032 SP 94.9 25.0 97.6 95 D6938 Pass
Location : Backfill for 8" ductile iron sewer line between manholes# 13 and 15, Elv/Depth :8 feet below finished grade
Comment : Gauge Serial No. :91643
02/05/2026 2 23.2 91.1 2025-032 SP 94.9 25.0 96.0 95 D6938 Pass
Location : Backfill of 8" ductile iron sewer line between manholes #13 and 15n manholes #, Elv/Depth :8 feet below finished grade
Comment : Gauge Serial No. :91643
02/05/2026 3 22.4 92.6 2025-032 SP 94.9 25.0 97.6 95 D6938 Pass
Location : Backfill of 8" ductile iron sewer line between manholes #14 and 15, Elv/Depth :6 feet below finished grade
Comment : Gauge Serial No. :91643
02/05/2026 4 23.0 92.8 2025-032 SP 94.9 25.0 97.8 95 D6938 Pass
Location : Backfill of 8" ductile iron sewer line between manholes #14 and 15, Elv/Depth :6 feet below finished grade
Comment : Gauge Serial No. :91643
02/05/2026 5 12.6 105.6 2025-035 SP 107.8 13.0 98.0 95 D6938 Pass
Location : Backfill of 8" ductile iron sewer line between manholes # 13 and 14, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :91643
02/05/2026 6 12.6 105.9 2025-035 SP 107.8 13.0 98.2 95 D6938 Pass
Location : Backfill of 8"ductile iron sewer line between manholes # 13 and 14, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, February 5, 2026
Reviewer Name / DateKenneth Mosman, February 16, 2026