Density Test Report

Date :02/20/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :02/20/2026 08:00
Onsite Hours :9:30
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :02/20/2026 17:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/20/2026 1 20 98.6 2025-023 SP 103.5 18.9 95.3 95 D6938 Pass
Location : Lot #39, Elv/Depth :1008.6
Comment : Reworked on Lot #39 from yesterday (retest) Gauge Serial No. :91487
02/20/2026 2 20.6 119.8 2025-023 SP 103.5 18.9 95.9 95 D6938 Pass
Location : Lot #39, Elv/Depth :1015.04
Comment : Gauge Serial No. :91487
02/20/2026 3 21.7 100.4 2025-023 SP 103.5 18.9 97.0 95 D6938 Pass
Location : Lot #40, Elv/Depth :1026.69
Comment : Gauge Serial No. :91487
Technician Signature / DateSamara Simha Reddy Kandi, February 20, 2026
Reviewer Name / DateKenneth Mosman, February 24, 2026